Backward Erosion Piping (BEP) is widely recognized as one of the most critical internal erosion mechanisms threatening river embankment stability. It typically develops during intense high-water events, with sand boils forming at the landside toe of the embankment. The process then progresses upstream, towards the river, gradually undermining the embankment integrity and ultimately leading to structural failure. This phenomenon has been observed in several sections of the main embankments along the Po River in Italy, as well as in other major water-retaining systems worldwide. This paper presents the rationale, design criteria and construction stages of a full-scale river embankment model, aimed both at analyzing the progression of BEP and assessing the effectiveness of a nature-based mitigation technology currently under development. The large-scale set-up will also serve as a robust benchmark to validate the results from small- and medium-scale physical modelling, recently carried out at the University of Bologna as part of the European project LIFE SandBoil. The experimental system, which has been recently completed, consists of a reinforced earth embankment, resting on a fine-grained foundation layer overlaying a permeable sandy unit, where underseepage occurs. Incremental water levels are imposed with an artificial impoundment on the upstream side. The monitoring system includes pore water pressure transducers and innovative distributed fibre optical sensors, to detect the development of erosive channels, as well as flow meters, to determine the outflow rate from a simulated exit point. This large-scale experimental system was built in an area within the AIPo Research Centre, in Boretto (Po river valley, Northern Italy). Prior to construction, a thorough characterization of the subsoil was conducted using both in-situ and laboratory tests.
Dodaro, E., Tumedei, E., Bertolini, I., Marchi, M., Gottardi, G., Tonni, L. (2026). Developing a full-scale experimental set-up for the simulation of backward erosion piping. Salisburgo : ÖGG (Austrian Society for Geomechanics) [10.53243/ICSMGE2026-2114].
Developing a full-scale experimental set-up for the simulation of backward erosion piping
Elena Dodaro
Primo
;Emanuele TumedeiSecondo
;Ilaria Bertolini;Michela Marchi;Guido GottardiPenultimo
;Laura TonniUltimo
2026
Abstract
Backward Erosion Piping (BEP) is widely recognized as one of the most critical internal erosion mechanisms threatening river embankment stability. It typically develops during intense high-water events, with sand boils forming at the landside toe of the embankment. The process then progresses upstream, towards the river, gradually undermining the embankment integrity and ultimately leading to structural failure. This phenomenon has been observed in several sections of the main embankments along the Po River in Italy, as well as in other major water-retaining systems worldwide. This paper presents the rationale, design criteria and construction stages of a full-scale river embankment model, aimed both at analyzing the progression of BEP and assessing the effectiveness of a nature-based mitigation technology currently under development. The large-scale set-up will also serve as a robust benchmark to validate the results from small- and medium-scale physical modelling, recently carried out at the University of Bologna as part of the European project LIFE SandBoil. The experimental system, which has been recently completed, consists of a reinforced earth embankment, resting on a fine-grained foundation layer overlaying a permeable sandy unit, where underseepage occurs. Incremental water levels are imposed with an artificial impoundment on the upstream side. The monitoring system includes pore water pressure transducers and innovative distributed fibre optical sensors, to detect the development of erosive channels, as well as flow meters, to determine the outflow rate from a simulated exit point. This large-scale experimental system was built in an area within the AIPo Research Centre, in Boretto (Po river valley, Northern Italy). Prior to construction, a thorough characterization of the subsoil was conducted using both in-situ and laboratory tests.| File | Dimensione | Formato | |
|---|---|---|---|
|
2026-Dodaroetal.ICSMGE.pdf
accesso aperto
Tipo:
Versione (PDF) editoriale / Version Of Record
Licenza:
Licenza per accesso libero gratuito
Dimensione
1.92 MB
Formato
Adobe PDF
|
1.92 MB | Adobe PDF | Visualizza/Apri |
I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.