We establish explicit socially optimal rules for an irreversible investment decision with time-to-build and uncertainty. Assuming a price sensitive demand function with a random intercept, we provide comparative statics and economic interpretations for three models of demand (arithmetic Brownian, geometric Brownian, and the Cox-Ingersoll-Ross). Committed capacity, that is, the installed capacity plus the investment in the pipeline, must never drop below the best predictor of future demand, minus two biases. The discounting bias takes into account the fact that investment is paid upfront for future use; the precautionary bias multiplies a type of risk aversion index by the local volatility. Relying on the analytical forms, we discuss in detail the economic effects. For example, the impact of volatility on the optimal investment is negligible in some cases. It vanishes in the CIR model for long delays, and in the GBM model for high discount rates.

Explicit investment rules with time-to-build and uncertainty / Aid R.; Federico S.; Pham H.; Villeneuve B.. - In: JOURNAL OF ECONOMIC DYNAMICS & CONTROL. - ISSN 0165-1889. - STAMPA. - 51:(2015), pp. 240-256. [10.1016/j.jedc.2014.10.010]

Explicit investment rules with time-to-build and uncertainty

Federico S.;
2015

Abstract

We establish explicit socially optimal rules for an irreversible investment decision with time-to-build and uncertainty. Assuming a price sensitive demand function with a random intercept, we provide comparative statics and economic interpretations for three models of demand (arithmetic Brownian, geometric Brownian, and the Cox-Ingersoll-Ross). Committed capacity, that is, the installed capacity plus the investment in the pipeline, must never drop below the best predictor of future demand, minus two biases. The discounting bias takes into account the fact that investment is paid upfront for future use; the precautionary bias multiplies a type of risk aversion index by the local volatility. Relying on the analytical forms, we discuss in detail the economic effects. For example, the impact of volatility on the optimal investment is negligible in some cases. It vanishes in the CIR model for long delays, and in the GBM model for high discount rates.
2015
Explicit investment rules with time-to-build and uncertainty / Aid R.; Federico S.; Pham H.; Villeneuve B.. - In: JOURNAL OF ECONOMIC DYNAMICS & CONTROL. - ISSN 0165-1889. - STAMPA. - 51:(2015), pp. 240-256. [10.1016/j.jedc.2014.10.010]
Aid R.; Federico S.; Pham H.; Villeneuve B.
File in questo prodotto:
Eventuali allegati, non sono esposti

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/11585/943360
 Attenzione

Attenzione! I dati visualizzati non sono stati sottoposti a validazione da parte dell'ateneo

Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus 13
  • ???jsp.display-item.citation.isi??? 10
social impact