The widespread adoption of small-scale distributed energy resources (DERs) amongst energy users has drastically changed the operation of distribution networks. To date, there has not been a consolidated model to incorporate the investment decisions of the end-users in the distribution network planning. The contribution of this paper is a distribution network planning model for the utility which considers the neighborhood energy trading (NET) as a platform for end-users to directly exchange energy between them. The proposed mixed-integer second-order cone programming (MISOCP) problem provides the optimal decisions for line and transformer upgrades, as well as for photovoltaic (PV) and battery in end-users’ premises. Moreover, it indicates a fair allocation of network charges among the participants to NET schemes. The simulation results on the IEEE-33 bus test system confirm the effectiveness of the proposed model in lowering the total cost of the planning and the operation. This platform can be used by government-owned utilities as a guide to avoid sunk investments while motivating the increased installation of renewable distributed generation and storage units by end-users.
Maleki Delarestaghi J., Arefi A., Ledwich G., Borghetti A. (2021). A distribution network planning model considering neighborhood energy trading. ELECTRIC POWER SYSTEMS RESEARCH, 191(February 2021), 1-10 [10.1016/j.epsr.2020.106894].
A distribution network planning model considering neighborhood energy trading
Borghetti A.Ultimo
2021
Abstract
The widespread adoption of small-scale distributed energy resources (DERs) amongst energy users has drastically changed the operation of distribution networks. To date, there has not been a consolidated model to incorporate the investment decisions of the end-users in the distribution network planning. The contribution of this paper is a distribution network planning model for the utility which considers the neighborhood energy trading (NET) as a platform for end-users to directly exchange energy between them. The proposed mixed-integer second-order cone programming (MISOCP) problem provides the optimal decisions for line and transformer upgrades, as well as for photovoltaic (PV) and battery in end-users’ premises. Moreover, it indicates a fair allocation of network charges among the participants to NET schemes. The simulation results on the IEEE-33 bus test system confirm the effectiveness of the proposed model in lowering the total cost of the planning and the operation. This platform can be used by government-owned utilities as a guide to avoid sunk investments while motivating the increased installation of renewable distributed generation and storage units by end-users.File | Dimensione | Formato | |
---|---|---|---|
borghetti_Distribution_postprint.pdf
Open Access dal 17/10/2022
Tipo:
Postprint
Licenza:
Licenza per Accesso Aperto. Creative Commons Attribuzione - Non commerciale - Non opere derivate (CCBYNCND)
Dimensione
924.69 kB
Formato
Adobe PDF
|
924.69 kB | Adobe PDF | Visualizza/Apri |
I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.